The gap between the plan line and actual is the campaign's schedule exposure.
Ranked by productivity. Availability & utilisation bars.
Stacked daily advance against the daily target line.
Metres per motor-hour when coring.
Metres drilled per calendar week against the weekly target — the truest read on momentum.
Each hole drawn at its true dip, depth to scale · solid = drilled, dashed = planned.
Averages across logged core runs.
Geotechnical rating bands: <25 Very Poor · 25–50 Poor · 50–75 Fair · 75–90 Good · >90 Excellent.
Daily breakdown hours by rig — persistent bars flag chronic loss.
How the 24-hour cycle was spent.
The 80/20 view: which faults cost the most rig-hours across the campaign. Fix the tall bars first.
Each hole across the calendar · solid = drilled window, striped = in progress. Vertical line marks today.
Every day resets to a zero-harm target.
Geology workflow completion per borehole.
At each hole's own recent advance rate.
UG_Daily-MIS_*.xlsx